STMicroelectronics detailed a program exceeding 100 million euros on Nov. 20, 2026, to expand production capabilities at its Rousset factory in France. The program began in 2025 and will continue through 2027, combining additional cleanroom space with automation rather than representing an entirely new investment commitment.
Factory changes
The company plans to add 1,000 square meters to an existing 10,000-square-meter cleanroom and upgrade equipment. It is also extending overhead wafer transport rails by 700 meters, beyond the existing 900 meters, to move material through production. ST says the changes are intended to improve factory productivity and responsiveness.
ST says the development has filled 100 positions through recruitment or internal transfers, with roughly 40 engineering and technician roles still open. Employee training accompanies the move toward automation, digital operations and process supervision. The site employs about 3,000 people.
Manufacturing strategy
ST detailed its global manufacturing redesign on April 10, 2025, setting different missions for its factories. At that time, ST said Rousset would retain 200-millimeter manufacturing and receive production transferred from other factories. Its division of work emphasized digital technologies in France, analog and power technologies in Italy, and mature technologies in Singapore.
The plan combined investment in 300-millimeter silicon wafer production with changes to mature manufacturing facilities. ST also described a shift away from repetitive manual work toward process control, automation and design. Those were company plans, not evidence that every transfer or workforce change has since been completed.
Reported results
More recent results provide the financial backdrop. On Oct. 29, ST reported third-quarter revenue of $3.76 billion, up 17.9% from a year earlier, and operating income of $367 million. Gross margin was 37.3%. These figures follow U.S. GAAP. The quarter ended Sept. 26, 2026. Chief Executive Jean-Marc Chery then described strong bookings and demand exceeding supply while linking capacity expansion to the company's manufacturing roadmap.